• Continued columns pour
  • Stormwater connections to Atlan tank – the tank is working as it should and has been capturing all the rainwater over the last week
  • Precast Panel Manufacture continued
  • Electrical In-Ground Services
  • Visit to the warehouse to inspect the completed panels
  • Works scheduled next week commencing 19th February include;
  • Strip Columns and prepare for the installation of the Precast panels
  • Installation of Precast panels -– weather permitting, these will commence delivery and installation on Tuesday through to Friday