17/2/2024 – Arise and Build Update

Continued columns pour Stormwater connections to Atlan tank – the tank is working as it should and has been capturing all the rainwater over the last week Precast Panel Manufacture continued Electrical In-Ground Services Visit to the warehouse to inspect the completed...

9/2/2024 – Arise and Build Update

Continued Reinforcement Fixing – Ground Floor Columns ⁠Installation of Ground Floor Column Reinforcement (to underside of Level 1) Formwork to Ground Floor Columns (to underside of Level 1) Lift Shaft Blockwork (to underside Level 1) Footpath Preparation (Outside Grid...

3/2/2024 – Arise and Build Update

Works on site this week included; Reinforcement Fixing – Ground Floor Slab “wings” Concrete Place – Ground Floor Slab “wings” Installation of Atlan Detention Tank Reinforcement Fixing – Ground Floor Columns “loose” God bless...