by VirginMary | Feb 3, 2024 | Uncategorized
Works on site this week included; Reinforcement Fixing – Ground Floor Slab “wings” Concrete Place – Ground Floor Slab “wings” Installation of Atlan Detention Tank Reinforcement Fixing – Ground Floor Columns “loose” God bless...