Activities for this past week included;

  • Retaining wall footings
  • Creating and testing pads in line with civil engineer advice
  • Structural engineer inspection (passed)
  • Poured retaining wall footings – concrete pour went ahead on 25/11

Planned activities for next week (weather permitting) are;

  • Bulk remove and stockpile unsuitable fill
  • Blockwork walls
  • Waterproofing