by VirginMary | Mar 8, 2024 | Uncategorized
The eastern and final part of our new church’s walls are being erected today. Pray that the Lord completes what He has begun. The eastern walls are almost finished and will be completed after laying the 1st floor slab in the coming weeks.Let us all give our...
by VirginMary | Mar 2, 2024 | Uncategorized
On the afternoon of Thursday 29/2/24, we had a great time touring our new church construction site with our project manager and IQ Construct representative. We gained a greater appreciation of how large this project is and how exciting it will be to finally...
by VirginMary | Feb 20, 2024 | Uncategorized
4 Tilt Panels installed so far. The rest will be installed by the end of the week. The Western, Northern and Southern walls of the church are almost completely erected. Please keep praying 🙏🏻✝️
by VirginMary | Feb 17, 2024 | Uncategorized
Continued columns pour Stormwater connections to Atlan tank – the tank is working as it should and has been capturing all the rainwater over the last week Precast Panel Manufacture continued Electrical In-Ground Services Visit to the warehouse to inspect the completed...
by VirginMary | Feb 9, 2024 | Uncategorized
Continued Reinforcement Fixing – Ground Floor Columns Installation of Ground Floor Column Reinforcement (to underside of Level 1) Formwork to Ground Floor Columns (to underside of Level 1) Lift Shaft Blockwork (to underside Level 1) Footpath Preparation (Outside Grid...