3/2/2024 – Arise and Build Update

Works on site this week included; Reinforcement Fixing – Ground Floor Slab “wings” Concrete Place – Ground Floor Slab “wings” Installation of Atlan Detention Tank Reinforcement Fixing – Ground Floor Columns “loose” God bless...

15/1/2024 – Arise and Build Update

Concrete footings for the foundation have been laid. Please keep this project in your prayers. We would love to see an indication of your financial support by completing the following form so we can gauge how much our congregation can contribute on a regular basis...

2/1/2024 – Arise and Build Update

Blessed Virgin Mary Family, I pray that everyone is off to a great start for 2024. We just wanted to update you about what has happened so far in the church building project. Work will recommence from Monday 8/1/24. Below is a table of what has been completed, what is...

27/11/2023 – Arise and Build Update

Activities for this past week included; Retaining wall footings Creating and testing pads in line with civil engineer advice Structural engineer inspection (passed) Poured retaining wall footings – concrete pour went ahead on 25/11 Planned activities for next week...