2/3/2024 – Arise and Build Update

On the afternoon of Thursday 29/2/24, we had a great time touring our new church construction site with our project manager and IQ Construct representative.  We gained a greater appreciation of how large this project is and how exciting it will be to finally...

17/2/2024 – Arise and Build Update

Continued columns pour Stormwater connections to Atlan tank – the tank is working as it should and has been capturing all the rainwater over the last week Precast Panel Manufacture continued Electrical In-Ground Services Visit to the warehouse to inspect the completed...

9/2/2024 – Arise and Build Update

Continued Reinforcement Fixing – Ground Floor Columns ⁠Installation of Ground Floor Column Reinforcement (to underside of Level 1) Formwork to Ground Floor Columns (to underside of Level 1) Lift Shaft Blockwork (to underside Level 1) Footpath Preparation (Outside Grid...

3/2/2024 – Arise and Build Update

Works on site this week included; Reinforcement Fixing – Ground Floor Slab “wings” Concrete Place – Ground Floor Slab “wings” Installation of Atlan Detention Tank Reinforcement Fixing – Ground Floor Columns “loose” God bless...

15/1/2024 – Arise and Build Update

Concrete footings for the foundation have been laid. Please keep this project in your prayers. We would love to see an indication of your financial support by completing the following form so we can gauge how much our congregation can contribute on a regular basis...