News & Stories
9/5/2024 – Arise and Build Update
From 27/4 till 9/5, we have seen the installation of the roof rafters and the arrival of the church tower domes to be installed later this month. May God complete what He has started. Donation Options: 1. Direct payment using your card number:...
23/4/2024 – Arise and Build Update: Message from our Fundraising Committee
Firstly, thank you so much for your incredibly generous donations. We have been truly overwhelmed with your support whether in prayer or donations thus far. As you can see the 1st stage of the church project is well on track to be finished by November. Let...
19/4/2024 – Arise and Build Update
On Friday 19/4/2024, the installation of the remaining tilt panels was completed giving us a greater glimpse into how the church will look when completed. The perimeter of the three main doors into the 1st floor main church are now visible. The three eastern niches...
29/3/2024 – Arise and Build Update
On Thursday 28/3, we finished pouring the remaining portion of the 1st floor where our 3 altars will be. Keep praying and giving. May the Lord complete His mighty wonders with us. Donation Options:1. Direct payment using your card...
23/3/2024 – Arise and Build Update
Last Friday 22/3, a large portion of the 1st floor was poured. This is the floor for our main church upstairs. Please pray that the Lord completes what He has started. Donation Options:1. Direct payment using your card...
8/3/2024 – Arise and Build Update
The eastern and final part of our new church's walls are being erected today. Pray that the Lord completes what He has begun. The eastern walls are almost finished and will be completed after laying the 1st floor slab in the coming weeks.Let us all give our 'five...
2/3/2024 – Arise and Build Update
On the afternoon of Thursday 29/2/24, we had a great time touring our new church construction site with our project manager and IQ Construct representative. We gained a greater appreciation of how large this project is and how exciting it will be to finally...
20/2/2024 – Arise and Build Update
4 Tilt Panels installed so far. The rest will be installed by the end of the week. The Western, Northern and Southern walls of the church are almost completely erected. Please keep praying 🙏🏻✝️
17/2/2024 – Arise and Build Update
Continued columns pour Stormwater connections to Atlan tank – the tank is working as it should and has been capturing all the rainwater over the last week Precast Panel Manufacture continued Electrical In-Ground Services Visit to the warehouse to inspect the completed...
9/2/2024 – Arise and Build Update
Continued Reinforcement Fixing – Ground Floor Columns Installation of Ground Floor Column Reinforcement (to underside of Level 1) Formwork to Ground Floor Columns (to underside of Level 1) Lift Shaft Blockwork (to underside Level 1) Footpath Preparation (Outside Grid...
3/2/2024 – Arise and Build Update
Works on site this week included; Reinforcement Fixing – Ground Floor Slab “wings” Concrete Place – Ground Floor Slab “wings” Installation of Atlan Detention Tank Reinforcement Fixing – Ground Floor Columns “loose” God bless ✝️
15/1/2024 – Arise and Build Update
Concrete footings for the foundation have been laid. Please keep this project in your prayers. We would love to see an indication of your financial support by completing the following form so we can gauge how much our congregation can contribute on a regular basis...